Pasadena Pools Project Schedule · Lot 216 · No. 2397

A schedule,
for the Lot 216
residence pool №2397

Every phase required to take the 36′ × 18′ pool from approvals to handover — the pool build, the site & hardscape work, and the water-feature change — sequenced end to end. Timing is shown in project weeks; add a start date to convert the whole plan to calendar dates.

QR code linking to the live schedule Scan for the live,
interactive schedule
Project
Lot 216 Residence
Location
White Pine Cyn · The Colony
Scope
Pool · Hardscape · Planting
Est. Duration
~29 weeks active
Leave the date blank for relative “Week X” timing. Pick a start date and everything shifts to the calendar. Add a winter pause and every phase on or after the pause date slides to spring.
Active work Draw Payment milestone Weather-sensitive Freeze risk at 8,300 ft Winter pause PP Pasadena Pools  ·  KL Kappus Landscape
The build, phase by phase
Tap any phase to expand its full task list. Phases overlap where trades allow. Durations carry a ~20% contingency, for a span of about 29 active weeks — plus any winter pause you add above.
Payments, tied to milestones
The same six milestones cover both contracts. Each draw applies the pool's percentages (25 / 25 / 25 / 22 / 3) across every scope, so Pasadena Pools and Kappus Landscape bill in step as each phase is signed off. Kappus figures include the 15% management fee. Figures rounded to the nearest dollar.
Milestone%Pool · PPSite & Land. · KLDraw total
1Deposit · Ph 025%$82,663$81,705$164,368
2Concrete · Ph 425%$82,663$81,705$164,368
3Tile / Equipment · Ph 7–825%$82,663$81,705$164,368
4Plaster · Ph 922%$72,744$71,901$144,645
5Final · Ph 113%$9,920$9,805$19,725
All-in total100%$330,653$326,822$657,475
Site & landscape budget · Kappus Landscape
The Kappus scope, grouped as budgeted, and mapped to the phases it supports. Amounts are budgets billed time-and-material on the 2-11-2026 plans and exclude the spa / hot-tub area — they'll be revised on the new ArcSitio plans and SARC approval.
Budget groupSupportsAmount
Plants, trees & native hydroseedPhase 10$16,812
Topsoil, wall backfill & compost mulchPhases 5–6, 10$11,235
Site labor, grading & haulingPhases 1–2, 6$10,855
Irrigation & sprinkler remodelPhase 10$10,705
Drainage — boxes, pipe & misc.Phase 6$2,000
Concrete — footer, rat-slab & flatworkPhases 5–6$32,896
Pool wall, stone veneer & caps, paving & coping, demo / access & utility subs (plumbing, electrical, trenching)Phases 1, 5–8$167,083
Portable restroomsDuration$560
Subtotal · Est. 7585$252,145
New 1,800-gal vault — excavation, backfill & plumbingPhase 1$20,400
Dismantle lower water feature & fill existing vaultPhase 1$10,800
ManagementPhase 1$848
Subtotal · vault Est. 7553$32,048
Kappus subtotal · Est. 7585 + 7553$284,193
Management fee · 15% (all Kappus scope)$42,629
Kappus Landscape total · incl. fee$326,822
Project cost summary
Pool constructionPasadena Pools · Est. 2397$330,653
Site, hardscape & plantingKappus Landscape · Est. 7585$252,145
Water-feature vault changeKappus Landscape · Est. 7553$32,048
Management fee · 15%Kappus Landscape scope$42,629
Project all-in (estimated)$657,475

On the Kappus figures

⚠ Weather & elevation risk — please read

This site sits at roughly 8,300 ft in Park City. Several finishing steps are temperature-sensitive and cannot be safely completed during a hard freeze:

If the shell and hardscape land late in the season, the weather-sensitive phases may pause over winter and resume in spring. Winter protection and snow removal are excluded from the current scopes.

Key assumptions

  • Final ArcSitio plans (water-feature change) issued and SARC-approved before Phase 1.
  • Excavated soil stays on-site; import/export would be a change order.
  • Gas & electrical brought to the equipment pad within 50 ft of the water's edge.
  • Machine access road available; existing radiant lines marked before digging.
  • Durations are working estimates and overlap where trades permit; weather, inspections, and long-lead equipment can shift dates.

Coordination notes

  • Pool scope by Pasadena Pools; site prep, walls, hardscape, utilities & planting by Kappus Landscape.
  • New 1,800-gal vault replaces the lower water feature to open patio space; existing vault buried on-site.
  • Existing hot tub, spa vault, radiant lines, concrete deck & trees to be protected/relocated.
  • Permitting, engineering, lighting & utility hookups confirmed before rough-in inspections.